01 July 2014 14:41

Dear Mrs Oliver,

I am writing in
response to your request for information (ref FOI 7834) regarding Additional
requests re Bredbury fire. We apologise for the delay in replying to your
request.

Further to your 6
emails of 19/09/13 from 11.38 am – 11.52 and your 2 emails 07/10/13 from 17.08 pm – 18.02 pm, the council has
collated those requests into one response.

The information
prepared by the relevant Council service is as follows:

· The
requested information is available to view on the scanned application files.
This can be viewed by contacting 0161 474 4810 to arrange an appointment to
view the electronic application files.

Request
1 –

Dear
FoI Officer

Regarding
this below, why were there no site notice or press notice dates?
Site
notice was posted on site and dated
26/3/10.
Press notice
from
Stockport Express 3/3/10. Both available to view on the
document viewer under reference DC043683.

Kind
regards

Sheila

Request
2 –

“2)
Prior to the approved materials recycling facility being brought into use, a
‘Statement of Operation’ which outlines:

(a)
how the site will operate;

(b)
the maximum volume of waste that will be processed;

(c)
the vehicle movements associated with this operation;

and
which shall be based on the information submitted in support of the
application, shall be submitted to the local planning authority for written
approval. The approved materials recycling facility shall then operate in
accordance with the approved ‘Statement of Operation’ at all times (or such
other statement that may be agreed in writing by the local planning authority).
The volume of waste processed at the facility shall not exceed that outlined in
the Statement of Operation unless otherwise agreed in writing by the local
planning authority.”

May
I see the Statement of Operation please.
Condition 2 (statement of
operation) – approved
27/08/10.
Statement is available to view on the document viewer under reference DC043683
(attached to email from Andrew Barton of Axis is attached to his email of
20th August 2010).

Kind
regards

Sheila

Request
3 –

“15)
No development shall take place until a method statement detailing how the
development will be constructed has been submitted to and approved in writing
by the local planning authority. The method statement shall include details on
traffic management and control measures, parking arrangements, details of
deliveries and details of how and where materials will be loaded, unloaded and
stored. Development of the site shall not proceed except in accordance with the
approved method statement.”

May
I see this statement please.
Condition 15 (traffic management
statement) – available to view on document viewer.

Kind
regards

Sheila

Request
4 –

17)
No development shall take place until a drawing outlining any areas within the
site that will be used for the storage of materials or other items has been
submitted to and approved in writing by the local planning authority. Any
materials / items to be stored within the site shall only be stored within
these areas.

May
I see this please.
Condition 17 (storage of materials) –
approved
23/7/10.
Drawing number 5337-P4-001 Rev 8 is available to view on the document viewer
under reference DC043683.

Kind
regards

Sheila

Request
5

17)
No development shall take place until a drawing outlining any areas within the
site that will be used for the storage of materials or other items has been
submitted to and approved in writing by the local planning authority. Any
materials / items to be stored within the site shall only be stored within
these areas.

· May
I see this please.
The requested information is available to view
on the scanned application files. This can be viewed by contacting 0161 474
4810 to arrange an appointment to view the electronic application files.

Request
1 –

Kind
regards

Request
6 –

19)
No part of the development shall be occupied until all works necessary to
prevent landfill gas migration into the development have been approved in
writing by the local planning authority and carried out in full. Following
completion of measures identified in the approved remediation scheme, a
verification report (referred to in
PPS23
as a validation report) that demonstrates the effectiveness of the remediation
carried out must be produced, and is subject to the approval in writing of the
local planning authority.

May
I see this please?
Condition 19 (measure to prevent migration of
landfill gas and verification report) – approved
17/2/12. The report (Gas Risk
Assessment – September 2009 – Geo Assist) is available to view on the document
viewer under reference DC041362 (as the completed development is a hybrid of 2
schemes approved under reference DC041362 and DC043683).

Request
7 –

Environmental Assessment:

Environmental
assessment not required

Dear
FoI Officer

What
was the name of the official who decided no environmental assessment was
needed?
Council Officers are not aware of any environmental assessment
having been carried out.

Any
refusal to respond will be forwarded to McDonald’s lawyers.

Yours

Sheila

Request
8 –

Dear
FoI Officer

Please
may I have contact details (email addresses) for all members of the group
referred to in this paragraph:-

External:

Rosemary.mccann@phe.gov.uk

George.kowalczyk@phe.gov.uk

Lorraine.lighton@phe.gov.uk

Simon.crozier@environment-agency.gov.uk

Sian.morrow@phe.gov.uk

heydonj@manchesterfire.gov.uk

carol.nadin@environment-agency.gov.uk

Internal:

Karen.dyson@stockport.gov.uk

Paul.kendal@stockport.gov.uk

Ian.odonnell@stockport.gov.uk

Jennifer.kilheeney@stockport.gov.uk

Megan.black@stockport.gov.uk

Sue.shore@stockport.gov.uk

n.folkes@manchester.gov.uk

Yours sincerely,

Marianne Lavin
Corporate Information Management Team
Stockport Council
Stockport SK1 3XE