Great Crested Newts
Dear FoI
Officer
The SEMMMS Project
Board meeting minutes from the 23/3/15 state:-
“10.7 BE noted
that GCN EPSL is a key risk in terms of timely receipt of
approved licence
from Natural England (NE), and NE response to
licence
application of bat works longer than statutory response
time.
CMS Mar /April
15″
Please let me know what
documents SMBC holds pertaining the the exact nature of the “risk in terms of timely receipt
of approved licence from Natural England”.
Secondly,
please let me know on what date the approved licence was received by the SEMMMS
Authorities/SMBC and please let me have a copy.
Many thanks
and kind regards.