No, more potential rising costs – yet money is tight

Bypass Posted on Fri, February 06, 2015 10:48

The proposed works clash with the

location of an ENWL Sub-Station. The

boundary fencing & arcing distances is

the issue.

Changing design

requirements

Increased design and

construction costs



Yep, you’ve guessed it – more rising costs.

Bypass Posted on Fri, February 06, 2015 09:41

The proposed works clash with the

location of an ENWL Sub-Station.

The boundary fencing & arcing distances is

the issue.

Changing design

requirements

Increased design and

construction costs



Flippin’ ‘eck, dodgy LibDem road for votes even interferes with airport landing lights. Strewth!

Bypass Posted on Fri, February 06, 2015 09:40

Only the incompetent LibDems could bring that about

The ex aircraft landing light that will be

located in the new central reserve of the

proposed works has to be lowered

every week for maintenance checks.

This will require traffic management, the

provision of which Manchester Airport

may object to.

Changing design

requirements

Increased design and

construction costs



Dodgy LibDem road for votes could land us with huge bill to Network Rail

Bypass Posted on Fri, February 06, 2015 09:37

Additional NR track possessions

required for construction/additional cost

to NR possessions. Bridge 14 and 15

SMBC issues still so separate risk

required.

Design phase preparation

works and consultation

activities

Increase in SMBC

payment to NR



We’re watching you LibDems, don’t you dare crush nesting birds

Bypass Posted on Fri, February 06, 2015 09:33

Nesting birds delaying the start of the

works

Construction start date being

driven by the statutory

process.

Programme delay and

additional cost incurred



I can see our council tax rising all for the glory of Stunell, Goddard et al

Bypass Posted on Fri, February 06, 2015 09:30

Construction costs arising from

unforeseen live utilities

Design phase preparation

works and consultation

activities

Increase cost as

Compensation Event

under the contract



Who will fund LibDem Vanity project cost overruns?

Bypass Posted on Fri, February 06, 2015 09:27

Statutory Undertaker diversions cost

underestimated

Design phase preparation

works and consultation

activities

Increased diversion costs Statutory

Undertakers

Again, money is tight. Who will pay for this LibDem vanity project?



Dodgy Stockport LibDems road for votes risk register

Bypass Posted on Fri, February 06, 2015 09:18

“Increased Thickness of thin Surfacing

required along the length of the

scheme.

Design phase preparation

works and consultation

activities

Scheme delayed and

budgets are compromised”

The bent Stockport LibDems are doing this on a shoestring. Who is going to pay cost overruns? I have been asking this all along.