Don’t Panic, Stockport LibDems have no idea what it will cost to replace the A6 MARR railway bridge

Bypass Posted on Thu, November 12, 2015 17:59

Dear Mrs Oliver,

I write regarding your request received on the 28th
October 2015. I have provided the Council’s response as follows:

The cost of the bridge is still subject to completion of detailed
design and final approvals from Network Rail; therefore this information is not
currently available as the associated costs are still in development and would
not be disclosed until appropriate sign-offs from all parties. The cost of the
bridge and associated risk allowances are covered within the overall scheme
budget.

I hope this is helpful.

Kind regards

Anwar

Anwar Majothi

Corporate Complaints Manager (CSS)



Don’t panic, the dodgy Stockport LibDems are moving the Manchester Airport oil pipeline

Bypass Posted on Wed, November 11, 2015 19:51

But even though Stockport Council has a legal duty to keep information in a manageable form, they can’t let me see even one piece of information on the moving of this vital oil pipeline.

Will the LibDem incompetents make a mess of this too, like the A6 MARR railway bridge? You betcha they will.

Dear Mrs Oliver,

I am sorry it was not clarified to you previously,
however the Council’s response to your request below is effectively the same
line as its response with the OPA; that,

There are a number of parties who were involved in
that process that are no longer part of the project team, which would add
further time, resource and expense, in addition to the numerous persons
involved in this process that are retained as part of the A6MARR project team.
Therefore the Council considers that the 18 hours exemption applies regarding
your request to see the communication between the project team and the
contractors.

Yours sincerely,

Anwar Majothi

Corporate
Complaints Manager (CSS)

Stopford
House

Stockport
Council

SK1
3XE



As with the toxic waste dump school, Mr Majothi doesn’t think he should answer

Bypass Posted on Tue, November 10, 2015 06:43

Dear Mrs Oliver,

I reply in response to your email below. Please accept my
apologies for the delay in replying.

I am afraid that the time limit would still exceed 18 hours to
source the information you are requesting. This is because the work would
entail liaison with a number of officers involved and sifting through
information that can be released and information that would need to be withheld.

I am sorry that I cannot be of further assistance regarding this
request.

Yours sincerely,

Anwar Majothi

Corporate Complaints Manager (CSS)

Stopford House

Stockport Council

SK1 3XE

Tel: 0161 474 3182

Mobile: 07800 618371

From: Sheila
Oliver
Sent: 20 October 2015 18:27
To: Anwar Majothi <
Subject: RE: Bramhall Oil Terminal pipeline sold by the MOD to the
Spanish on the orders of the LibDem Coalition Government

Dear Mr Majothi

Thank you for your
response. I can narrow the request down. Any correspondence this
year regarding the diversion of the Manchester Airport oil pipeline to and from
Stockport Council with regards to the A6 MARR.

It is a current project, so
that’s not too onerous.

Sheila



Bypass and pothole spending SMBC

Bypass Posted on Mon, November 09, 2015 18:51



A6 Marr railway bridge latest update

Bypass Posted on Mon, November 09, 2015 18:06

Dear Mrs Oliver,

I provide Stockport Council’s response regarding your request
below and you may also receive a similarly worded response from Cheshire East
Council.

Cheshire East and Stockport Council are currently applying for
planning permission regarding the construction of the Hazel Grove/Buxton
Railway Bridge. This is being applied for as a result of the applicant working
closely with Network Rail throughout the development of the original approved
design for the Hazel Grove/Buxton Railway Bridge (as per the planning
permission granted by Stockport Council in June 2014) and subsequently in the
development and detail of the design to arrive at the design that is the
subject of this planning application. Throughout this period of technical
design development and Network Rail liaison, a number of issues have been
identified which have influenced the design and led to changes to the original
approved design.

·
Requirement
to accommodate provision for a three-metre wide access track beneath the bridge
on the east side of the A6MARR carriageway, as requested by Network Rail.
This is for a possible future footpath (FP75) diversion, which would allow
Network Rail to close the nearby uncontrolled pedestrian crossing as part of a
national drive to eliminate this type of crossing.

·
Effects
of ground conditions which necessitated an increase in the retained height for
track support between piles in the previous design.

·
To
address Network Rail concerns regarding increased retaining wall height for
track support between supporting piles.

·
To
de-risk the Network Rail possession programme for bridge
construction/installation.

·
To
accommodate other Network Rail requests, including provision of a permanent
bearings inspection gallery at each abutment.

It was therefore concluded that the structure design would need to
be altered, hence the requirement for the recent planning permission as
referenced.

There are no documents pertaining to a potential 2 year delay
referenced within the FOI. Currently the works are still progressing as
programmed.

Yours sincerely,

Anwar Majothi

Corporate Complaints Manager (CSS)



A6 MARR Railway Bridge Planning Application

Bypass Posted on Tue, October 27, 2015 19:26

http://planning.stockport.gov.uk/PlanningData/applicationDetails.do?activeTab=externalDocuments&keyVal=DCAPR_125798



Only now mid October 2015 apply for planning permission for A6 MARR railway bridge.

Bypass Posted on Sun, October 18, 2015 08:43

“Erection of a railway bridge to accommodate the Hazel
Grove/Buxton Railway, including an access track below the proposed bridge..”
Application No DC/059877.



Constant querying of FOIA questions without justification to imply nuisance requests

Bypass Posted on Sun, October 11, 2015 10:13

Email sent – 11/10/15 at 10.00

Dear Mr Majothi

Thank you for your email below
dated 5/10/15 at 09.53

I sent you this clarification on
the Friday 2nd October at 17.11:

“Dear Mr Majothi

As long as all the extra work/project delays
are identified, the costs can be calculated and independently audited.

I am very keen to protect the public purse;
always have been.

I recall the A6 bypass when costs rose from
£179m to £1billion over a short space of time, and Councillor Derbyshire
et al were completely unconcerned by this. Evidence available on request

Sheila”

I look forward to your supplying the
information requested.

Kind regards

Sheila

From: Anwar Majothi
Sent: 05 October 2015 09:53
To: ‘Sheila Oliver’
Subject: RE: Project change orders – master matrix A6 MARR

Dear Mrs Oliver,

Thank you for your email.

The clarification is needed to help narrow down the search for the
information you have requested. I kindly await your response.

Yours sincerely,

Anwar Majothi

Corporate Complaints Manager (CSS)

Stopford House

Stockport Council

SK1 3XE

Tel: 0161 474 3182

Mobile: 07800 618371

http://www.stockport.gov.uk

From: Sheila
Oliver

Sent: 02 October 2015 17:01
To: Anwar Majothi
Subject: RE: Project change orders – master matrix A6 MARR

Dear Mr Majothi

Why are you requesting the
context of where have taken this from?

Sheila

From: Anwar Majothi
Sent: 02 October 2015 09:47
To: ‘Sheila Oliver’
Subject: RE: Project change orders – master matrix A6 MARR

Dear Mrs Oliver,

Firstly, just to let you know that I am currently assisting the
Information Governance team.

I have liaised with the TCAP
& A6MARR team regarding your request below and they are seeking further
clarification of what you are specifically requesting and the context from
where you have taken this from.

I can however confirm that scheme costs are not being forecast to
overrun.

I look forward to hearing from you further.

Yours sincerely,

Anwar Majothi

Corporate Complaints Manager (CSS)

Stopford House

Stockport Council

SK1 3XE

Tel: 0161 474 3182

Mobile: 07800 618371

http://www.stockport.gov.uk

From: Sheila
Oliver
Sent: 29 September 2015 18:03
To: FOI Officer <
Cc: Charlie Sunderland
Subject: Project change orders – master matrix A6 MARR

Dear FoI Officers

Please may I see the master matrix detailing the project
change orders of the A6 MARR. I am, as you know, concerned about cost
overruns and how the council taxpayers of Cheshire East, Manchester and
Stockport will be able to afford them.

Kind regards

Sheila